Distribution of the substructure and installation
The spacing between brackets, profiles, and clips are determined by factors such as the facade cladding design, the type of wall and/or building structure, and the specific location of the building.
The vertical profiles are securely installed on the wall using dead-load and wind-load brackets properly anchored to the substrate. These brackets ensure that the vertical profiles are properly leveled, allowing for the correction of any irregularities in the support wall behind the facade to be cladded.
Installation method
The installation of panels should begin from the bottom rows and progress upward, ensuring the panels rest on the lower clips that have already been installed.
Once the brackets and profiles are securely in place, attach the clips using flat-head screws to prevent interference with the panel. The type of clips used will vary depending on the panel’s location and its position.
Before placing the panel, apply a bead of adhesive onto the vertical profiles. Once the lower clips are in place and the adhesive has been applied, position the Neolith panel correctly and press it firmly until it makes contact with the adhesive. Finally, secure the upper clips of the panel, and repeat the process for the remaining panels.
For installing the final panels on the facade—such as at the top of the facade, at junctions with drip edges, or near terraces— follow this sequence for securing the upper clips:
- Attach the clips to the profile using screws placed in the lower section of the slotted holes of the clip. Do not fully tighten these screws to allow for future adjustments.
- Position the Neolith panel using the lower clips as support.
- Slide the upper clips downward until they align with the panel.