Distribution of the substructure and installation
Spacing between profiles depends on the facade cladding design (joint location), as well as the type of substrate, project wind loads, and structural assumptions.
Vertical profiles are anchored directly to the substrate with the appropriate fasteners.
A pull-out test may be required to determine the substrate’s load-bearing capacity before defining the profile spacing.
How to apply chemical fixation
Chemical fixation consists in the direct application of adhesive and double-sided self-adhesive strip to the vertical profiles. For optimal adhesion, it is essential to pre-treat both the Neolith panels and the vertical profiles. The general steps to be carried out are described below:
01. Cleaning
Both the profiles (once fixed) and the panels must be free of dust or any other contaminants that could compromise the bond. For extremely dirty panels, clean using acetone or methyl ethyl ketone (avoid using turpentine).
02. Application of the activator
After allowing the cleaning products to evaporate for 10 minutes, apply the activator to both the profile and the back of the panel, focusing on the area that will align with the profiles. Use disposable cellulose paper to apply the activator, rubbing from top to bottom and always in a single direction (avoid circular motions). Repeat the application as many times as needed until the paper no longer gets stained. Use a new piece of paper for each application.
03. Application of the primer
Once the activator has evaporated, apply a single coat of primer using a brush over the entire surface in contact with the adhesive, from top to bottom (not in a circle). It must be applied both on the profile and on the surface of the panel that will be in contact with the adhesive.
04. Application of the double-sided adhesive strip
Once the primer has dried (approx. 25 minutes, depending on the manufacturer and atmospheric conditions), apply the double-sided adhesive strip vertically and continuously on the profiles. This strip is used for the initial fastening of the cladding panels until complete curing (or polymerization) of the adhesive, and to ensure the correct dimensions of the adhesive bead.
05. Adhesive application
The adhesive should only be applied vertically and continuously, forming a triangular bead using the special V-shaped nozzle. It must always be applied between +5 °C (41 °F) and +35 °C (95 °F) of ambient temperature. Typically, two lines of elastic adhesive are applied along the vertical “T” profile, while a single line is applied on the “L” profile. Depending on the manufacturer, the adhesive must be applied within a maximum of 2 hours after the primer has been applied.
06. Panel installation
The Neolith panel should be placed within 10 minutes of applying the adhesive, after removing the protective film from the double-sided strip. Once the panel is correctly positioned, press it firmly onto the profiles to ensure full contact with the strip. After the panel has made contact with the strip, no adjustments can be made.