HC-R System


Fastening system

Chemical attachment system + reinforcing clip

Fastening type

Concealed fasteners

Thickness

6mm+

Outlet

Adjustable build-up

Certification

Sitema HC-R

The HC-R system is a hybrid solution, an enhanced version of the HC system that incorporates a security clip (mechanical anchorage) in a concealed manner. This additional reinforcement improves the system’s overall performance. It is designed for the exterior cladding of facades using 6 mm thick Neolith panels.

For safety, a fiberglass mesh is applied to the back of the panels to prevent any fragments from detaching in case of accidental breakage.

This system includes dead load and wind load brackets, vertical profiles, and a chemical adhesion system for attaching the Neolith cladding panels. The chemical bonding process involves pre-treating both the profiles and the panels to improve adhesion, followed by the use of double-sided adhesive tape and adhesive.

A minimum joint of 5 mm, both horizontally and vertically, is recommended between the Neolith panels to ensure proper installation.

Hidden system with chemical fixing and security clip

Spacing between profiles depends on the facade cladding design (joint location), as well as the type of substrate, project wind loads, and structural assumptions.

Vertical profiles are installed onto the dead-load and wind-load brackets, following the facade joints.

These brackets ensure proper leveling of the vertical profiles, allowing for corrections to any irregularities in the supporting wall of the façade.

Before applying the pre-treatments for bonding, the panels are grooved at a 45° angle to accommodate the security clips.

A small amount of adhesive is applied within the groove to fix the clip and seal the area. The number of clips required will depend on the dimensions of each panel, ensuring stability and reinforcement.

A pull-out test may be required to determine the substrate’s loadbearing capacity before defining the profile spacing.

How to apply chemical fixation

Chemical fixation consists in the direct application of adhesive and double-sided self-adhesive strip to the vertical profiles. For optimal adhesion, it is essential to pre-treat both the Neolith panels and the vertical profiles. The general steps to be carried out are described below:

01. Cleaning

Both the profiles (once fixed) and the panels must be free of dust or any other contaminants that could compromise the bond. For extremely dirty panels, clean using acetone or methyl ethyl ketone (avoid using turpentine).

After allowing the cleaning products to evaporate for 10 minutes, apply the activator to both the profile and the back of the panel, focusing on the area that will align with the profiles. Use disposable cellulose paper to apply the activator, rubbing from top to bottom and always in a single direction (avoid circular motions). Repeat the application as many times as needed until the paper no longer gets stained. Use a new piece of paper for each application.

Once the primer has dried (approx. 25 minutes, depending on the manufacturer and atmospheric conditions), apply the double-sided adhesive strip vertically and continuously on the profiles. This strip is used for the initial fastening of the cladding panels until complete curing (or polymerization) of the adhesive, and to ensure the correct dimensions of the adhesive bead.

The adhesive should only be applied vertically and continuously, forming a triangular bead using the special V-shaped nozzle. It must always be applied between +5 °C (41 °F) and +35 °C (95 °F) of ambient temperature. Typically, two lines of elastic adhesive are applied along the vertical “T” profile, while a single line is applied on the “L” profile. Depending on the manufacturer, the adhesive must be applied within a maximum of 2 hours after the primer has been applied.

The Neolith panel should be placed within 10 minutes of applying the adhesive, after removing the protective film from the double-sided strip. Once the panel is correctly positioned, press it firmly onto the profiles to ensure full contact with the strip. After the panel has made contact with the strip, no adjustments can be made.

Other installation systems

VM System

VM System

Sistema HC

HC System

Sistema HC Slim

HC Slim System

Sistema HR

HR System

Sistema HU

HU System

Sistema Strongfix

Strongfix System